								The 
								reconstruction compensations were paid according 
								to the statistics that included the damaged 
								buildings listed in detailed forms. The forms 
								required visiting each damaged unit, surveying 
								the damages of paint/electrical equipment/water 
								cycles/furniture etc… The buildings were later 
								subjected to a financial round, starting with 
								pricing, into auditing, and then documenting and 
								archiving them, followed by tables including 
								names and fiscal numbers. Compensations were 
								paid in accordance with the fiscal numbers, with 
								taking into consideration that not any side can 
								directly start reconstructing due to the 
								hugeness of this file, for more than 120,000 
								units were affected including houses, shops, 
								institutions and others, yet they should hasten 
								its implementation. Jihad al Binaa dealt with 
								the owners as if they were the managers of their 
								own reconstruction projects, and this file was 
								covered in six months. 
								
								
								   |